I posted these photos on another large scale forum but thought I’d also share them here, too. I’ve hired a masonry contractor to build the support base for my garden railway due to my sloping backyard. The third day was completed today and one more to go. Here’s the photo chronology of the work:
-
Photo #1: The layout design.
-
Day One progress. Photo #2, 3, 4.
-
Day Two Progress. Photo #5 - 10.
-
Day Three Progress. Photo #11 - 14.
Comments: My contractor originally estimated 2 1/2 dump truck loads of dirt to fill in the retaining wall to be level. It required FOUR - costing me $350 per load. To get around two large trees and their roots, I’m using two double LGB truss bridges which are four feet length each, so for the two main lines around the perimeter of the new RR will require four LGB bridges per bridge (eight total for traversing the two trees)…but it will actually add character to the layout. There will be 3 inches of crushed stone #9 on top of the dirt within the retaining wall. Bill, my contractor’s tractor operator…he moved the four dump truck loads of dirt into the retaining wall and then the crushed stone #9.
- Day Four: The contractor will finish the work next Monday and then my work begins laying track…I’m using AML brass flex track. First task, install and test the outer loop of the double mainline.